LQCD Change Management Process
The Change Management Process is defined in the LQCD Project Execution Plan (PDF) (Word).
A Change Request (CR) to the project baseline is approved only after an e-mail verification to the project office (by default to the Associate Contractor Project Manager, or, if that person is not available, to the Contractor Project Manager) is received from the appropriate approval authority. The approved CR then becomes a Change Authorization (CA). Necessary scope, cost and schedule adjustments are made only after the CA is in place
.
Change Authorizations
CR ID |
Baseline |
Date Requested |
Approval Authority |
Approval Date |
CR06_01 |
V0.0 |
12/8/05 |
CCB chair |
2/16/06 |
CR06_02 |
V0.0 |
6/12/06 |
CCB chair |
7/20/06 |
CR06_03 |
V0.0 |
6/12/06 |
CCB chair |
7/20/06 |
CR07_01 |
V0.1 |
2/24/07 |
Federal Project Director |
6/21/07 |
CR ID |
Baseline |
Date Requested |
Approval Authority |
Pending Change Requests
|
|
|
|
|
|
|
|
|
|
|
|